PRAIRIE
WATERS NORTH CAMPUS PROJECT
Brighton,
CO
| Project
Highlights:
- 34 miles of buried pipeline will be installed
- 60-inch diameter mortar lined, urethane-coated steel pipe
- Providing backfill compaction testing, concrete testing,
and geotechnical trouble-shooting
|
|
FITZGERALDS
CASINO EXPANSION AND ROHLING INN REBUILD
Black
Hawk, CO
|
Project
Highlights:
- Provided geotechnical design services.
- Project included excavation of existing soil and rock.
- Services were followed through with backfill compaction
testing, concrete testing, mortar and grout testing, and
reinforcing steel inspection.
|
|
MAPLE
GROVE WATER TREATMENT PLANT EXPANSION
Lakewood,
CO
| Project
Highlights:
- A 15 MGD water treatment plant
- 800,000 gallon cast-in-place buried clearwell
- Providing foundation inspection, backfill compaction testing,
concrete testing, and geotechnical trouble-shooting
|
|
|
|