25TH
AVENUE GRAVEL PIT
WATER
STORAGE RESERVOIR AND INLET/OUTLET STRUCTURES
Greeley,
Colorado
Lyman
Henn provided engineering services for design and construction of
an 8,460-ft-long slurry wall enclosing a 70-acre gravel pit to create
a water storage reservoir. This reservoir will serve to provide
water re-timing ability for the City. A slurry wall which encloses
two adjacent reclaimed gravel pits was designed by Lyman Henn. Work
performed included a supplemental geotechnical investigation, site
specific surveying, a technical feasibility study, an initial design
and cost estimate, an evaluation of design/build contracting, and
preparation of final design and specifications. Lyman Henn provided
construction monitoring and quality control during slurry wall construction.
Lyman Henn designed and performed the Initial Liner Test on the
lined reservoir as required by the State Engineer's Office. Lyman
Henn performed part-time construction monitoring during inlet/outlet
construction to monitoring geotechnical components to the construction.

|
|