|
LAKE
PLEASANT PIPELINE TUNNEL
Phoenix,
Arizona
The
project is part of an eight mile long, 76-in. inside diameter water
transmission pipeline from a new water treatment plant in northwestern
metropolitan Phoenix . The tunnel was required to minimize or eliminate
construction disturbance to an existing City of Phoenix Mountain
Preserve Park with sensitive desert vegetation. The tunnel alignment
is 1,700-ft long in variably weathered granitic bedrock and is designed
to parallel the existing Carefree Highway and the northern boundary
of the Mountain Preserve. The alignment passes below Skunk Creek
and a small knoll comprising the northern portion of the Mountain
Park . The west shaft is 60-ft deep constructed through dense alluvial
soils and completely weathered bedrock and the east portal approximately
40-ft deep constructed through weathered rock. Tunnel excavation
used drill and blast and roadheader methods, placement of temporary
excavation support followed by pipe placement and annular backfill
using cellular concrete. Subsurface explorations were performed
using portable drill rigs, carried by hand, to each drill hole location
to minimize disturbance to the Preserve. Tunnel design included
provisions for noise mitigation and portal/shaft were located outside
the Park boundary to minimize disturbance.
Lyman
Henn provided oversight of subsurface investigations performed by
a local geotechnical engineering firm, prepared full contract documents
for design of the tunnel and provided designer coordination and
field inspection services during tunnel construction. The tunnel
design was done under a very aggressive schedule to accommodate
the overall project schedule requirements for pipeline completion.
Construction services included full-time resident inspection of
tunnel excavation, support pipe installation and backfill grouting
construction activities.

|
|