TRILBY
ROAD/FOSSIL CREEK FLOOD CONTROL DISTRICT
Fort
Collins, Colorado
Lyman
Henn provided geotechnical and tunnel design services for this project,
which involves multiple box culvert crossings beneath Trilby Road
and two 10-ft-diameter tunnels beneath a UPRR embankment. A field
investigation program including test borings and geophysics was
conducted to characterize subsurface conditions, which consisted
of cohesive alluvium overlying claystone bedrock. The tunnel crossing
beneath the railroad embankment is a challenging aspect of the project
due to a buried trestle bridge located inside the embankment at
an unknown location. The tunnel will be constructed using a open
face shield and hand spades and small excavation equipment. Project
deliverables included a geotechnical and tunneling design report,
alternatives analysis, technical specifications, tunnel detail drawings,
and an estimate of probable construction cost.

|
|